1952

The Mackle brothers donated the current church property of 328,006 sq.ft. to the parish and named it St. Agnes after their mother's patron saint.

1954

The current church building was built as a parish hall.

1973

The school opened for 7th & 8th grade.

1991

The current middle school building was built.

1996

The school expanded to include PK3-8th.

2001

The current elementary school building was built.

2007

The pastoral center was built.

2017

Beautification committee was created to beautify the campus with simple paint and plant alternatives. However, they quickly realized that there were major issues and challenges.

Challenges

Church not built on pilings causing floor to break and sink.
Roof has no remaining life & asbestos.
Electrical problems.
Electrical problems.
Capacity is insufficient.
Traffic for the community.
LEFT: Security & safety deficiency. RIGHT: Insufficient Parking.
Choir emergency exit & low railing.
Windows
No impact windows & A/C escapes.
No gym – home games in Miami Lakes (26 miles away – 35-50 mins approx.).

THE INITIAL SOLUTION & obstacles

Created a building committee:

A building committee was created to determine how best to address these challenges.

The initial idea was to remodel the church even though it would only solve some of the issues. Remodeling plans were presented to the Village, however, this exceeded the 50% FEMA rule. The structure needed to meet the new building code which meant elevating it. The only way to solve the challenges was to build a new church.

Remodel Church: Cost $5MM:

  • Would solve the choir staircase, ADA bathroom, plumbing, electrical & add a few pews.
  • Didn’t solve many of the needs.

Went to Village of KB with plans to remodel.

Allow remodeling if we bring the entire church up to code (50% rule):

  • Install sprinkler system.
  • Hurricane impact windows.
  • Elevate to 15ft.

Conclusion:

  • Not worth putting in so much money into such an old building.
  • Cannot bring it up to code by remodeling.